Posted on 10 Jul 2008
South Korean steel giant Posco’s $12 billion project in
Grant of the two clearances would be major step forward in
salvaging the steel major’s 12 million tonne (mt) steel project that has been
in the midst of controversy ever since an MoU was inked in 2005. The company
hopes to begin work on the first phase of 4 mt capacity immediately after
getting land and mining clearance and targets to complete it ahead of original
schedule of 36 months.
“The government is according utmost priority to the Posco
project. In this regard its proposal for prospecting licence for Khandhadhar
iron ore block in Orissa would be given as soon as the state sends its
recommendations to the Centre. The Supreme Court’s Central Empowered Committee
(CEC) on environment has also said that it would recommend for land diversion
clearance once there is clarity on mining lease for the project,” an official
source connected with the project told ET.
The project requires captive iron ore mines with reserves of
about 600 mt. While the state has identified three blocks at Khandhadhar,
Melang Toli and Thakurani for the project, only Khandhadhar is close to be
being offered to the steel maker. The state is conducting a public hearing from
other applicants for the same block and expects to conclude the process by July
26, before finalising the name of Posco as the most deserving applicant for the
iron ore block with a firm investment commitment and project development plan.
Though the mining block has a reserve of about 200 mt of iron ore, sufficient
to meet just one-third of Posco’s total requirement, it could support entire
first phase of the steel project.
On the forest diversion plan clearance, the matter has
reached the final stages as both state and the Centre have cleared the
application and CEC is waiting for clearance of mining rights before
recommending PL for Khandhadhar in favour of Posco. The company has submitted its
application of forest diversion plan for changing the land use of 3,093 acre of
forest land on its project site of 4,004 acres. This clearances would mean that
Posco would be in possession of over 3,500 acre of government land soon. It
would then begin the process to acquire the remaining about 450 acre of private
land.
“We could begin work on the project even if we get a portion
of the total project land,” a Posco spokesperson said. Anticipating final lot
clearances for the project soon, the company has already finalised a
rehabilitation and resettlement plan that has even bettered the one finalised
by the state government.